Kohler — Load Connections

Installation · Paralleling box load camlock connectors

From a Kohler service manual covering: 125REZGT, 145REOZT4, 175REOZT4, 30REZG, 35 REOZT4, 45 REOZT4, 50REZG, 55REOZT4, 70REZGT, GM88594-KP1-QS, REOZT4. Check it applies to your exact model before use.

Applies to: Kohler 125REZGT, Kohler 145REOZT4, Kohler 175REOZT4, Kohler 30REZG, Kohler 35 REOZT4, Kohler 45 REOZT4, Kohler 50REZG, Kohler 55REOZT4, Kohler 70REZGT

Before you start

  • Multiple power sources can automatically energize the distribution bus. Disconnect all power sources before connecting to the distribution bus.

Procedure

  1. Remove the camlock security guard from one row of connectors for each generator and store the guard.
  2. Connect the load side ground (green) camlock cables to the distribution bus and then to the paralleling box.
  3. Connect the load side neutral (white) camlock cables to the distribution bus and then to the paralleling box.
  4. Connect the load side L1 (black), L2 (red), and L3 (blue) camlock cables to the distribution bus and then to the paralleling box.

Full service-parts list: Kohler 125REZGT →, Kohler 145REOZT4 →, Kohler 175REOZT4 →, Kohler 30REZG →, Kohler 35 REOZT4 →, Kohler 45 REOZT4 →, Kohler 50REZG →, Kohler 55REOZT4 →, Kohler 70REZGT →

Source: Kohler service manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.