Kohler — Load Connections
Installation · Paralleling box load camlock connectors
From a Kohler service manual covering: 125REZGT, 145REOZT4, 175REOZT4, 30REZG, 35 REOZT4, 45 REOZT4, 50REZG, 55REOZT4, 70REZGT, GM88594-KP1-QS, REOZT4. Check it applies to your exact model before use.
Applies to: Kohler 125REZGT, Kohler 145REOZT4, Kohler 175REOZT4, Kohler 30REZG, Kohler 35 REOZT4, Kohler 45 REOZT4, Kohler 50REZG, Kohler 55REOZT4, Kohler 70REZGT
Before you start
- Multiple power sources can automatically energize the distribution bus. Disconnect all power sources before connecting to the distribution bus.
Procedure
- Remove the camlock security guard from one row of connectors for each generator and store the guard.
- Connect the load side ground (green) camlock cables to the distribution bus and then to the paralleling box.
- Connect the load side neutral (white) camlock cables to the distribution bus and then to the paralleling box.
- Connect the load side L1 (black), L2 (red), and L3 (blue) camlock cables to the distribution bus and then to the paralleling box.
Full service-parts list: Kohler 125REZGT →, Kohler 145REOZT4 →, Kohler 175REOZT4 →, Kohler 30REZG →, Kohler 35 REOZT4 →, Kohler 45 REOZT4 →, Kohler 50REZG →, Kohler 55REOZT4 →, Kohler 70REZGT →
Source: Kohler service manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.