Kohler — Prepare the Site, Outdoor Installations, Enclosed Units

Installation · generator set site

From a Kohler service manual covering: 10REOZD, 15REOZD, 20REOZD. Check it applies to your exact model before use.

Applies to: Kohler 10REOZD, Kohler 15REOZD, Kohler 20REOZD

Procedure

  1. Obtain a building permit and contact local utility companies to mark underground pipes and cables.
  2. Clear combustible materials from an area at least 2.4 m (8 ft.) beyond the exhaust end.
  3. Spread a 76-mm (3-in.) thick layer of gravel to support the concrete mounting pad.
  4. Lay a concrete pad that extends at least 152 mm (6 in.) beyond the generator set on all sides.
  5. Include mounting bolts at locations shown on the dimension drawing.

Specs & values

  • Location at least 0.9 m (3 ft.) from any building or structure
  • Minimum 2.4 m (8 ft.) clearance beyond the exhaust end

Full service-parts list: Kohler 10REOZD →, Kohler 15REOZD →, Kohler 20REOZD →

Source: Kohler service manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.