Home›Repair guides›Generac›Retransfer and Shutdown (Manual Transfer Switch)

Generac QT 1.6L 20kW — Retransfer and Shutdown (Manual Transfer Switch)

Operation · Generator and transfer switch

For the Generac QT 1.6L 20kW, from the Generac owner's manual.

Applies to: Generac QT 1.6L 20kW, Generac In Line engine

Procedure

  1. Set the standby generator's main line circuit breaker to its OFF (or OPEN) position.
  2. Manually move the transfer switch handle to its UTILITY (NORMAL) position.
  3. Turn ON the utility power supply to the transfer switch.
  4. Let the generator run at no-load for a few minutes to stabilize internal temperatures.
  5. Shut down the generator.

Full service-parts list: Generac QT 1.6L 20kW →

Source: Generac owner's manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.