Home›Repair guides›Generac›Engine Start-up and Transfer (Manual Transfer Switch)

Generac 005336-0 / 005337-0 — Engine Start-up and Transfer (Manual Transfer Switch)

Operation · Manual transfer switch / generator

For the Generac 005336-0 / 005337-0, from the Generac owner's manual.

Applies to: Generac In Line engine

Before you start

  • Do not crank the engine continuously for longer than 30 seconds.
  • Do not attempt manual operation until all power supplies to the transfer switch have been positively turned off.
  • Transfer switch enclosure doors should be kept closed and locked.

Procedure

  1. Turn OFF or disconnect the utility power circuit to the transfer switch.
  2. Set the transfer handle to its UTILITY (NORMAL) position.
  3. Set the standby generator's main line circuit breaker to OFF (OPEN).
  4. Start the generator.
  5. Let engine stabilize and warm up and check all instrument and gauge readings.
  6. Move the transfer switch manual handle to its STANDBY (GENERATOR) position.
  7. Set the standby generator's main line circuit breaker to ON (CLOSED).

Source: Generac owner's manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.