Generac 005210-0 — Preparation for Start-up (start-up checklist)
Installation · Generator / battery charger / control panel
For the Generac 005210-0, from the Generac owner's manual.
Applies to: Generac In Line engine
Before you start
- Before working on the generator, ensure the AUTO/OFF/MANUAL switch is in the OFF position.
- Ensure the 120VAC supply to the battery charger is switched OFF.
Procedure
- Ensure that the 120VAC circuit breaker to the battery charger is open.
- Remove the fuse from the control panel (15 Amp ATO fuse for H-100 and R-100).
- Connect the battery cables to the battery. Attach negative battery cable last.
- Close the 120VAC circuit breaker to the battery charger.
- Measure the voltage at the battery before and after the charger is turned on.
- Verify all AC electrical connections are tight at the circuit breaker and transfer switch.
- Visually inspect entire area looking for loose paper, plastic wrappings, leaves, etc.
- Check all hoses, clamps and fittings for leaks or damage.
- Check all electrical plugs; ensure each plug is seated correctly and fully inserted.
- Verify the AUTO/OFF/MANUAL switch is in the OFF position.
- Open the valve to the engine fuel line.
- Bleed the fuel system of air (necessary for long fuel lines).
- Open the generator main line circuit breaker.
- Connect a manometer to the gas line and record the static pressure; it must be as listed in the Specifications.
- Insert the fuse into the control panel. Move the AUTO/OFF/MANUAL switch to MANUAL. The engine should now crank and start.
Tools required
- Manometer Amazon
Tool links are Amazon searches (affiliate links); manufacturer special tools may only be available from a dealer.
Specs & values
- Static gas pressure must be as listed in the Specifications section
Source: Generac owner's manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.