Fischer Panda PMS 4200 FCB / Panda PMS 4200 FCB — Insulation test
Installation · electrical system
For the Fischer Panda PMS 4200 FCB / Panda PMS 4200 FCB, from the Fischer Panda operator's manual.
Applies to: Fischer Panda Panda PMS 4200 FCB, Farymann 18W430 engine
Procedure
- Switch off all on-board electrical devices.
- Start generator.
- Measure AC voltage between generator housing and AC-Control box; between generator housing and ground.
- Measured voltage must not exceed 50 mV.
- Check safety systems and leakage current relay if installed.
- Verify all electrical devices are connected to common ground.
Tools required
- Voltmeter Amazon
Tool links are Amazon searches (affiliate links); manufacturer special tools may only be available from a dealer.
Specs & values
- Measured voltage must not exceed 50mV
Full service-parts list: Fischer Panda Panda PMS 4200 FCB →
Source: Fischer Panda operator's manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.