Fischer Panda — Insulation Test

Installation · electrical system

From a Fischer Panda owner's manual covering: 12000NE-15000NE, Panda 12.000NE, Panda 14.000NE, Panda 15.000NE. Check it applies to your exact model before use.

Browse Fischer Panda generators & specs →

Procedure

  1. Switch off all on-board electrical devices.
  2. Start generator.
  3. Measure AC voltage between generator housing and AC-Control box, and between generator housing and ground.
  4. Measured voltage must not exceed 50 mV.
  5. Check safety systems and leakage current relay if installed.

Tools required

Tool links are Amazon searches (affiliate links); manufacturer special tools may only be available from a dealer.

Specs & values

  • Measured voltage must not exceed 50 mV

Source: Fischer Panda owner's manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.