Procedure

  1. If generator is in area regularly below 40°F (4°C), select 50 second warm up by moving jumper on JP2 from '20' to '50' position
  2. Place 2 position switch to 'NG' or 'LP' as appropriate
  3. Place 3 position switch to match KW rating of installed generator
  4. Connect terminals A-A (24 VAC, air conditioner contactor control) in series with A/C contactor control circuit
  5. Connect terminals B-B (1 Amp 125 VAC) in series with installer-supplied contactor for a large load
  6. Tighten all wire connections/fasteners to proper torque per enclosure label

Source: Briggs & Stratton service manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.