HomeRepair guidesINSTALLATION

Transfer Switches - LakeShore — INSTALLATION

A Transfer Switches - LakeShore service procedure — check it applies to your exact model before use.

Browse Transfer Switches - LakeShore generators & specs →

Procedure

  1. 1. To remove unit from enclosure: Push tab on right to swing unit to the left and remove.
  2. 2. Mount the enclosure at eye level using screws or other suitable fastening device. Bring
  3. 3. Install 9 volt alkaline battery (not supplied) by sliding battery cover in direction of arrow
  4. 4. Reinstall unit by reversing step #1 above and connect wires to unit as per suggested wir-
  5. 1. Press MODE key until display shows CLK.
  6. 2. Press DAY key to select current day. Press HOUR key to select current hour. Check A
  7. 1. If display does not show SCH, press mode key until display shows SCH.
  8. 2. Press HOUR and MIN keys for the first ON setting (check for AM or PM).
  9. 3. Press ENTER key to store the information and display will indicate it is ready to receive
  10. 4. Press HOUR and MIN keys for the first OFF setting. Then press ENTER key to store the
  11. 5. Proceed for up to 7 ON and 7 OFF setpoints. Then press MODE key and unit will go to the
  12. 1. Press mode key until display shows SKIP. Press DAY key and M (Monday) starts flashing.
  13. 1. CLOCK - ALTER TIME
  14. 2. SCHEDULE - REVIEW
  15. 3. SCHEDULE - MODIFY
  16. 4. SKIP DAYS - ADD/DELETE
  17. 9. TROUBLESHOOTING GUIDE
  18. 1. A wiring diagram for the switch must be available.
  19. 2. Normal and Emergency voltage and frequency must be available and within the
  20. 3. Control circuit voltage (if transformers are used) must be 110 to 125 volts.

Source: manual:Styles 2, 3 and T-200 New Manual.pdf. Figures and steps are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.