  1. 4.1 General
  2. 4.2 Mounting Location
  3. 4.3 Unpackaging and Inspection
  4. Step 1: Carefully uncrate the transfer switch. If damage is visible,
  5. Step 2: Open the door and visually verify that there are no broken
  6. Step 3: A label on the door provides specifications for your trans-
  7. Step 4: Remove any braces or packing used to protect the trans-
  8. 4.4 Mounting Procedure
  9. Step 1: Mounting and cabling access is best provided by remov-
  10. 9.3 for cover removal instructions.
  11. Step 2: Gently maneuver the switch into its location using all of
  12. Step 3: Bolt the enclosure to the base. Use separate cleats
  13. Step 4: Tighten bolts to 50 ft-lbs (68 Nm).
  14. Step 5: Double check to ensure that all packing and shipping .
  15. 4.5 Power Cable Connections
  16. Step 1: Verify that the line and load cables comply with applica-
  17. Step 2: Verify that the transfer switch rated current and voltage
  18. Step 3: After the transfer switch is mounted, provide the conduit
  19. Step 4: Test all power cables before connecting them to the unit
  20. Step 5: Carefully strip the insulation from the power cables.

Source: manual:Magnum ATS Instructions.pdf. Figures and steps are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.