  1. 4.5 Power Cable Connections
  2. Step 1: Verify that the line and load cables comply with applica-
  3. Step 2: Verify that the transfer switch rated current and voltage
  4. Step 3: After the transfer switch is mounted, provide the conduit
  5. Step 4: Test all power cables before connecting them to the unit
  6. Step 5: Carefully strip the insulation from the power cables.
  7. Step 6: Tighten the cable lugs to the torque identified on the label
  8. Step 7: Make the necessary connections of any options using the
  9. Step 8: Connect the engine start wires to the logic connector
  10. 4.6 Voltage Selection Adjustment .
  11. 4.7 Mounting the Switching Device in the Drawout
  12. 4.8 Wiring
  13. 4.8.1 Engine Start Connection
  14. 4.8.2 ALARM CONTACTS (CLOSED TRANSITION ONLY)
  15. 5.1 General
  16. 25. An indicator window shows whether the switch is open or
  17. 3.2.2). An indicator window shows whether the switch is open
  18. 5.2 Automatic Transfer Switch
  19. 2. Open both switching devices
  20. 4. Verify source availability

Source: manual:Magnum ATS Instructions.pdf. Figures and steps are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.