Procedure

  1. Check to ensure that the normal switching device is in the CLOSED position. This should have been done in Step 1a.
  2. Initiate an automatic transfer operation from the normal to emergency power source.
  3. Initiate an automatic transfer operation back to the normal power source after timing delays.

Source: manual:New AgSwitch Instruction Manual.pdf. Figures and steps are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.