Kohler — Real (kW) Load Sharing Calibration

Adjustments · Decision-Maker 6000 kW Load Sharing

From a Kohler service manual — check it applies to your exact model before use.

Browse Kohler generators & specs →

Before you start

  • Do not reconnect Modbus cable to MCP until setup complete and computer disconnected.

Procedure

  1. Set the ramp rate to the desired setpoint.
  2. Place the first generator set online via the Start button.
  3. Place a second generator online; set its sync control to auto.
  4. Place load on the system and verify both generators share equally.
  5. Press the unload button for one generator and verify ramp-down.
  6. Verify the generator ramps to the sharing setpoint.
  7. Verify frequency remains within configured deadband.
  8. Update all identical generators with the same settings.

Tools required

  • Kohler SiteTech Software Amazon

Tool links are Amazon searches (affiliate links); manufacturer special tools may only be available from a dealer.

Specs & values

  • Load bank at least 70% of total generator capacity

Source: Kohler service manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.