Kohler — Load Management Configuration

Operation · MCP 3000 Load Management

From a Kohler service manual — check it applies to your exact model before use.

Browse Kohler generators & specs →

Procedure

  1. Configure the priority for each load control relay (add/shed contact).
  2. Configure the expected load of each load control relay.
  3. Configure generator online add delay.
  4. Configure delay for GOL add before kW capacity add.
  5. Configure the kW capacity time between adds.
  6. Configure maximum percentage to auto load generators.
  7. Configure under frequency load shed priority, setpoint, and time delay.
  8. Configure kW overload setpoint and time between sheds.

Specs & values

  • Priority 2 through 8 acceptable
  • Priority 1 is not shed

Source: Kohler service manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.