Kohler — DPS Commissioning Sequence
Installation
From a Kohler service manual — check it applies to your exact model before use.
Browse Kohler generators & specs →
Before you start
- Setup and commissioning only to be performed by qualified personnel.
Procedure
- Perform generator set start-up, calibration, and commissioning.
- Perform ATS initial setup.
- Verify DPS system component interconnect wiring.
- Review and set initial system parameters.
- Perform MCP 3000 power up and initial checks.
- Verify generator set stand-alone operation.
- Set up and verify synchronization.
- Set up generator and load management; verify no load test.
Source: Kohler service manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.