  1. Perform generator set start-up, calibration, and commissioning.
  2. Perform ATS initial setup.
  3. Verify DPS system component interconnect wiring.
  4. Review and set initial system parameters.
  5. Perform MCP 3000 power up and initial checks.
  6. Verify generator set stand-alone operation.
  7. Set up and verify synchronization.
  8. Set up generator and load management; verify no load test.