Generac — Utility Voltage Checks

Testing & diagnosis · ATS terminals / 3 phase power monitor relay

From a Generac service manual — check it applies to your exact model before use.

Browse Generac generators & specs →

Before you start

  • Failure to turn off the UTILITY supply before working on the UTILITY connections of the ATS will result in extremely dangerous and possibly fatal electrical shock.
  • The transfer switch is now electrically hot.

Procedure

  1. Turn ON UTILITY power supply to transfer switch.
  2. With accurate AC voltmeter measure across ATS lugs N1-N2, N2-N3, N1-N3.
  3. Measure across ATS lugs N1-N, N2-N, N3-N.
  4. Locate 3 phase power monitor relay; verify LED green and ON (208 Vac) or NORM indicator green and ON (480 Vac).
  5. If LED is not ON, rotate adjustment potentiometer counter-clockwise until LED turns ON.
  6. Verify utility phase rotation matches generator using a phase rotation indicator.

Tools required

Tool links are Amazon searches (affiliate links); manufacturer special tools may only be available from a dealer.

Specs & values

  • Factory setting 80% of nominal voltage
  • 208 Vac system dropout = 166 Vac
  • 480 Vac system dropout = 384 Vac

Source: Generac service manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.