Generac — Transfer Switch Installation

Installation

From a Generac service manual — check it applies to your exact model before use.

Browse Generac generators & specs →

Before you start

  • Hazardous voltages present inside transfer switch enclosures
  • Turn off main circuit breaker before starting installation

Procedure

  1. Select mounting location on left or right side of load center for 24 in. flexible conduit harness
  2. Remove load center front cover and a knockout matching the harness conduit fitting size
  3. Shorten wiring harness/conduit if needed
  4. Attach wiring harness to load center; mount transfer switch to wall using template
  5. Remove transfer switch cover; install conduit/wire between Power Inlet Box and transfer switch
  6. Connect generator ground wire to green wire, neutral to neutral bar, black to Meter A, red to Meter B; reinstall cover
  7. Remove wires for relocated loads from load center breakers; connect blue harness wires (A4-B6) per Table 2
  8. Remove two single-pole breakers and install new 60A 2-pole breaker; terminate harness black/white/green wires
  9. Reinstall load center cover; turn ON main breaker, branch breakers, and UTIL MAIN in transfer switch

Tools required

Tool links are Amazon searches (affiliate links); manufacturer special tools may only be available from a dealer.

Source: Generac service manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.