Generac — 12
For these Generac models: EcoGen 6kW Generator, GT-530.
Applies to: Generac Ecogen 6Kw Generator, Generac Gt 530
Procedure
- 5. When certain that input voltage is compatible with battery charger ratings, turn OFF the power supply to the generator.
- 6. On the generator panel, set the Auto/Off/ Manual switch to MANUAL. The engine should crank and start.
- 7. Let the engine warm up for about five minutes to allow inter- nal temperatures to stabilize. Then, set the generator’s main circuit breaker to its ON (or closed) position. Proceed with caution! Generator power volt- age is now supplied to the inverter. Contact with live inverter parts will result in danger- ous and possibly fatal electrical shock.
- 8. Connect the AC voltmeter test leads across terminal lugs E1 and neutral. Voltage reading should be 125-120 volts AC.
- 9. Set the generator’s main circuit breaker to its OFF (or OPEN) position. Let the engine run at no-load for a few minutes to stabilize internal engine generator temperatures. 10. Set the generator's AUTO/OFF/MANUAL switch to OFF. The engine should shut down. NOTE: It is important not to proceed until certain that generator AC voltage and frequency are correct and within the stated limits.
- 2.4 GENERATOR TESTS UNDER LOAD To test the generator set with electrical loads applied, proceed as follows:
- 1. Set generator’s main circuit breaker to its OFF (or OPEN) posi- tion.
- 2. Turn OFF all breakers on the load center of the inverter (if equipped).
- 3. Set the generator's AUTO/OFF/MANUAL switch to MANUAL. The engine should crank and start immediately.
- 4. Let the engine stabilize and warm up for a few minutes.
- 5. Set the generator’s main circuit breaker to its ON (or CLOSED) position. The inverter is now powered by the standby genera- tor.
- 6. Turn ON the load center of the inverter system.
- 7. Connect an accurate AC voltmeter and a frequency meter across terminal lugs at the inverter. Voltage should be greater than 120 volts and frequency • should be 60 Hz.
- 8. Let the generator run at full rated load for 20-30 minutes. Listen for unusual noises, vibration or other indications of abnormal operation. Check for oil leaks, evidence of overheat- ing, etc.
- 9. When testing under load is complete, turn OFF electrical loads. 10. Set the generator's main circuit breaker to its OFF (or OPEN) position. 11. Let the engine run at no-load for a few minutes. 12. Set the AUTO/OFF/MANUAL switch to OFF. The engine should shut down.
- 2.5 CHECKING AUTOMATIC OPERATION To check the system for proper automatic operation, proceed as follows:
- 1. Set generator’s main circuit breaker to its OFF (or OPEN) posi- tion.
- 2. Check that the AUTO/OFF/MANUAL switch is set to OFF.
- 5. Turn ON the power supply to the battery charger, using the means provided (such as a line circuit breaker).
- 6. Set the generator's main circuit breaker to its ON (or CLOSE
Source: manual:696471058185_use.pdf. Figures and steps are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.