Generac 004583-0 — Installing the Manual Transfer Switch (overview)
Installation · Manual transfer switch with load center
For the Generac 004583-0, from the Generac owner's manual.
Browse Generac generators & specs →
Before you start
- Switch service main circuit breaker to OFF before removing cover or any wiring of main distribution panel.
Procedure
- Locate transfer switch with load center within one foot of main distribution panel.
- Mount power inlet box over pre-drilled hole and seal with silicone caulk.
- Connect black, red, and white wires to same color coded lugs; torque to 25 in/lbs.
- Install customer-supplied 60 Amp double pole circuit breaker in main panel.
- Connect white wire to neutral bar and green wire to ground bar.
- Connect black and red wires to 60 Amp double pole circuit breaker.
Tools required
- Drill, drill bits, hole saw Amazon
- Open-end or adjustable wrenches Amazon
- Socket wrenches or nut drivers Amazon
- Standard and Phillips screwdrivers
- Sledge hammer, level, pencil Amazon
- Channel-lock pliers, wire cutters/strippers Amazon
- Safety goggles Amazon
Tool links are Amazon searches (affiliate links); manufacturer special tools may only be available from a dealer.
Specs & values
- Torque lug screws to 25 in/lbs
- Circuit breaker 60 Amp double pole
Source: Generac owner's manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.