Before you start

  • ANCHORING THE UNIT IS EXTREMELY IMPORTANT.
  • GROUNDING THE UNIT IS EXTREMELY IMPORTANT - potential electrical shock hazard.

Procedure

  1. Locate unit on level ground, lined up with towers, minimum 300 feet from first tower.
  2. Anchor unit opposite pulling force with anchors holding three times pulling machine rating.
  3. Ground unit to ground rod or electrical neutral using grounding bars provided.
  4. Put hazard barrier around perimeter to keep unauthorized personnel away.
  5. Perform daily preventive maintenance.

Tools required

Tool links are Amazon searches (affiliate links); manufacturer special tools may only be available from a dealer.

Specs & values

  • Anchors must hold three times the maximum rating of the pulling machine

Source: Caterpillar owner's manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.