Aurora Generators — Operational Checks

Testing & diagnosis · ATS contactor, generator voltage regulator

From a Aurora Generators service manual covering: EGSC100ASE, EGSC200ASE, EGSC400ASE, EGSCA100ASE, EGSCA200ASE, EGSCA400ASE. Check it applies to your exact model before use.

Browse Aurora Generators generators & specs →

Before you start

  • This will simulate an interruption of the utility power source.

Procedure

  1. Open the service entrance disconnect circuit breaker originally closed to simulate an interruption of the utility power source.
  2. After a time delay (based on the generator settings), the standby generator engine will start.
  3. Use a voltmeter to measure line-to-line and line-to-neutral voltages across the generator line terminals; adjust the voltage regulator if necessary.
  4. ATS Time Delay Normal (Utility) to Emergency (Generator) (TDNE) begins timing; after time out the contactor switches from UTILITY to GENERATOR.
  5. Close the service entrance disconnect circuit breaker.
  6. ATS Time Delay Emergency (Generator) to Normal (Utility) (TDEN) timer begins; the contactor switches from GENERATOR to UTILITY and the generator will shut down after a cool down period.

Tools required

Tool links are Amazon searches (affiliate links); manufacturer special tools may only be available from a dealer.

Source: Aurora Generators service manual. Steps and values are as documented; always cross-check against the official manual and any later revisions for your exact serial number before servicing.

More Aurora Generators repair guides →