The GA-420 is a 25.6 L 1-cylinder engine. It powers generator sets from Generac, including the 7 kW PowerPact and 7.5 kW PowerPact. It holds 1.1 L (0.3 gal) of oil.

Also known as: GA-420

25.6 L
Displacement
1
Cylinders
1.1 L
Oil capacity

Engine specifications

Oil capacity1.1 L
Displacement25.6 L
Cylinders1

Generator sets powered by this engine

2

Common problems

7
  • Unit consumes large amounts of oil.
    Cause: 1. Engine overfilled with oil. 2. Engine breather defective. 3. Improper type or viscosity of oil. 4. Damaged gasket, seal or hose.
    Fix: 1. Adjust oil to proper level. 2. * 3. See Engine Oil Requirements. 4. Check for oil leaks.
  • No transfer to standby after utility source failure.
    Cause: 1. Main line circuit breaker is in the OFF (or OPEN) position. 2. Defective transfer switch coil. 3. Defective transfer relay. 4. Transfer relay circuit open. 5. Defective control logic board.
    Fix: 1. Reset circuit breaker to ON (or CLOSED). 2. * 3. * 4. * 5. *
  • No AC output from generator.
    Cause: 1. Main line circuit breaker is in the OFF (or OPEN) position. 2. Generator internal failure.
    Fix: 1. Reset circuit breaker to ON (or CLOSED). 2. *
  • Generator is set to OFF, but the engine continues to run.
    Cause: 1. Controller wired incorrectly 2. Defective control board.
    Fix: 1. Repair wiring.* 2. Replace control panel*
  • Engine will not crank.
    Cause: 1. Fuse blown. 2. Loose, corroded or defective battery cables. 3. Defective starter contact. 4. Defective starter motor. 5. Dead battery.
    Fix: 1. Correct short circuit condition by replacing 7.5 Amp fuse in generator control panel. 2. Tighten, clean or replace as necessary.* 3. *See #2. 4. *See #2. 5. Charge or replace battery.
  • Engine starts hard and runs rough.
    Cause: 1. Air cleaner plugged or damaged. 2. Defective spark plug(s). 3. Fuel pressure incorrect. 4. Fuel selector in wrong position.
    Fix: 1. Check / replace air cleaner. 2. Clean, re-gap or replace plug(s). 3. Confirm fuel pressure to regulator is 10–12 in. water column (19-22 mm mercury) for LP, and 5–7 in. water column (9-13 mm mercury) for natural gas. 4. Turn fuel conversion valve to correct position.
  • Engine cranks but will not start.
    Cause: 1. Out of fuel. 2. Defective fuel solenoid (FS). 3. Defective spark plug(s). 4. Valve clearance out of adjustment. 5. In cold weather condition.
    Fix: 1. Replenish fuel / Turn on fuel valve. 2. * 3. Clean, re-gap or replace plug(s). 4. Reset valve clearance. 5. Install recommended cold weather kit.

Compiled from service & troubleshooting documentation across every generator set that uses the GA-420.

Maintenance schedule

ItemSpecCapacityPart #Interval
Air filter0E9371A50 hr Amazon eBay $19.99
Fuel filter
Oil filterGenerac oil kits meet minimum API Service Class SJ, SL or better and include an air filter
BatteryGroup U1, 12 Volts, 300 CCA minimum
OilSAE 30 above 32F(0C); SAE 10W-30 between 40 and -10F(4 and -23C); Synthetic SAE 5W-30 for all temp ranges; API SJ, SL or better1.2 L (1.2 qt)100 hr
Spark plugGap 0.030 in (0.76 mm); torque 20-22 ft-lb (27-30 Nm)0J5584300 hr eBay

Pooled from every document that names this exact engine — confirm the interval and part number against your unit's serial number.

Service intervals

24
ItemActionHoursMonthsNotes
Break-in maintenance (oil change, valve clearance, tune-up)Other20 hrFirst service — 20-hour break-in interval
Oil, oil filter and air filter replacementReplace20 hrFirst service — Recommended after the first 20 hours after installation
Valve AdjustmentAdjust20 hrFirst service — Recommended after the first 20 hours of operation
Oil levelCheck24 hr1 moMonthly or 24 hours of continuous operation
Air cleanerClean50 hr3 mo3 months / 50 hours - clean
OilChange100 hr6 moSevere duty: hot/dusty ambient (above 85F/29.4C) change every 3 months or 50 hours
Scheduled MaintenanceOther100 hr12 mo1 Year / 100 Hour Maintenance Due indicated on control panel
Spark plugInspect100 hr6 mo6 months or 100 hours - inspect
Air cleanerReplace300 hr12 mo1 year / 300 hours - replace
Spark plugChange300 hr12 mo1 year or 300 hours - change
Valve clearanceCheck300 hr12 moCheck first at 20 hours, then every 300 hours
Battery - check charge stateCheck12 moYearly
Battery - remove corrosion, ensure drynessClean12 moYearly
Battery charge stateCheck12 moYearly
Battery corrosionInspect12 moYearly; remove corrosion, ensure dryness
Battery electrolyte level (unsealed batteries only)Check6 moEvery 6 months
Battery inspection and charge checkCheck12 moRecommended every year for the life of the battery
Battery terminalsClean12 moClean and tighten yearly
Battery terminals - clean and tightenClean12 moYearly
Break-in MaintenanceOtherFirst service — Perform break-in maintenance when control panel indicates BREAK-IN MAINTENANCE DUE
Electrolyte level (unsealed batteries)Check6 moEvery 6 months
Fuel lines and connectionsInspect1 moMonthly; contact dealer if repair needed
General Condition - vibration, noise, leakageInspect1 moMonthly; contact dealer if repair needed
Vibration, noise, leakageInspect1 moMonthly

Extracted from the manufacturer documentation linked to this model. Values are copied as printed; confirm against your unit's manual and serial number.

Service specifications

18
TypeItemValueUnitCondition
ClearanceSpark Plug Gap0.76mm (0.030 in)7 kW units
GapSpark plug gap0.030in (0.76 mm)
PressureFuel pressure to regulator (LP)10-12in. water column (19-22 mm mercury)
PressureFuel pressure to regulator (Natural Gas)5-7in. water column (9-13 mm mercury)
PressureLP Fuel Pressure to Regulator10-12in water column (19-22 mm mercury)LP gas
PressureNatural Gas Fuel Pressure to Regulator3.5-7in water column (9-13 mm mercury)Natural gas
SpeedGenerator output frequency under load240 volts, 60 Hzunder rated load
TorqueRocker Arm Jam Nut174in-lb (19.68 N-m)
TorqueRocker arm jam nut torque174in-lbs (19.68 Nm)
TorqueSpark Plug20-22ft/lb (27-30 Nm)
TorqueSpark plug torque20-22ft-lb (27-30 Nm)
TorqueValve Cover Fasteners35-62in/lb (4-7 Nm)
TorqueValve cover fasteners torque35-62in-lbs (4-7 Nm)cross pattern
Valve clearanceValve clearance0.002-0.004in (0.05-0.1 mm)engine cool
VoltageGenerator output voltage at no load (E1-E2)236–240volts ACat frequency 62–63 Hz, no load
VoltageGenerator output voltage, line-to-neutral (E1/E2-neutral)118–120volts AC
VoltageUtility power source voltage, line-to-line (N1-N2)240volts ACnominal
VoltageUtility power source voltage, line-to-neutral (N1/N2-neutral)120volts ACnominal, if wired with neutral

Extracted from the manufacturer documentation linked to this model. Values are copied as printed; confirm against your unit's manual and serial number.

Recommended fluids

FluidGradeStandardAmbientCapacityNotes
Engine oilSynthetic SAE 5W-30API SJ, SL or better1.1 L (1.2 qt)For all temperature ranges
Engine oilSAE 10W-30API SJ, SL or better-23°C to 4°C1.1 L (1.2 qt)Between 40F and -10F (4C and -23C)
Engine oilSAE 30 above 32F (0C); 10W-30 between 40F and -10F (4C and -23C); Synthetic 5W-30 for all temperature ranges (after 100 hours)API SJ, SL or betterabove -23°C1.2 Qt (1.1 L)No special additives
Engine oilSAE 30API SJ, SL or betterabove 0°C1.1 L (1.2 qt)Above 32F (0C)
FuelLP Vapor, min. 2,500 BTU/ft3 (93.15 MJ/m3)Required pressure 10–12 in H2O (19–22 mm HG); minimum tank 250 gal (946 L), or 1050 lb (476 kg) vertical tank
FuelNatural Gas, min. 1,000 BTU/ft3 (37.26 MJ/m3)Required pressure 5–7 in. water column (9–13 mm mercury)
FuelNatural gas (min 1,000 Btu/cu ft / 37.26 MJ/m3) or LP gas vapor (min 2,500 Btu/cu ft / 93.15 MJ/m3); factory set to run on natural gasMinimum LP tank size of 250 gallons (946 liters) recommended if converting from natural gas to LP

Extracted from the manufacturer documentation linked to this model. Values are copied as printed; confirm against your unit's manual and serial number.

Fault codes

12
CodeNameMeaningSeverityAction
1 Year / 100 Hour Maintenance DueRegular Maintenance Due1 year / 100 hour maintenance due (solid)InfoPerform scheduled maintenance, clear maintenance due light
BATTERY PROBLEMBattery Problem WarningBattery problem existsWarningContact IASD
Break-in Maintenance DueBreak-in Maintenance Due20 hour break-in maintenance due (flashing)InfoPerform break-in maintenance, clear maintenance due light
CHARGER PROBLEMCharger WarningCharging problem existsWarningContact IASD
HIGH TEMPERATUREHigh Temperature AlarmTemperature levels are excessive; unit shuts down during operationShutdownCheck ventilation around generator, intake, exhaust and rear; if no obstruction, contact IASD
LOW OIL PRESSURELow Oil Level AlarmUnit will not start in AUTO with utility loss; oil level insufficientShutdownCheck oil level, add oil per Engine Oil Requirements; if correct, contact IASD
NO LEDs LITNo Power / FuseUnit will not start in AUTO with utility loss; no LEDs litShutdownCheck ATO 7.5 Amp fuse, replace with same type if bad; contact IASD if fuse is good
NOT ACTIVATEDNot ActivatedUnit will not start in AUTO with utility loss; screen says unit not activatedInfoRefer to activation section in Installation Manual
OVERCRANKOvercrank AlarmOvercranking condition exists; unit will not start in AUTO with utility lossShutdownVerify fuel line shutoff valve ON, clear alarm, attempt start in MANUAL; if fails, contact IASD
OVERSPEED/UNDERSPEEDOverspeed/Underspeed AlarmOverspeed or underspeed condition existsShutdownContact IASD
RPM SENSE LOSSRPM Sensor AlarmUnit was running and shuts down; RPM sensor problem exists; attempts to restartShutdownClear alarm, remove household loads, put back in AUTO and restart; if not start, contact IASD
WIRING ERRORWiring ErrorWiring error detected; unit will not start in AUTO with utility lossShutdownContact IASD

Extracted from the manufacturer documentation linked to this model. Values are copied as printed; confirm against your unit's manual and serial number.

Procedures

12
Adjust Valve Clearance adjustment

Tools: 10mm wrench, feeler gauge, torque wrench

  1. Cool engine before adjustment
  2. Remove enclosure lid, fasteners, back panel
  3. Remove spark plug wire and spark plug
  4. Remove 4 screws attaching valve cover, discard gasket
  5. Loosen rocker jam nut with 10mm wrench
  6. Turn pivot ball stud while checking clearance with feeler gauge to 0.002-0.004 in (0.05-0.1 mm)
  7. Hold pivot ball stud, tighten rocker arm jam nut to 174 in-lbs (19.68 Nm)
  8. Recheck clearance
  9. Install new valve cover gasket
  10. Install valve cover, tighten fasteners in cross pattern to 35-62 in-lbs (4-7 Nm)
  11. Install rubber plug into fan screen
  12. Install spark plug and wire
  13. Install back panel and enclosure top lid
  14. Place generator in AUTO
Adjusting Valve Clearance adjustment

Tools: 13 mm Allen wrench, Feeler gauge

  1. Ensure engine is at 60-80 F (16-27 C).
  2. Remove enclosure lid and back panel if not already removed.
  3. Ensure spark plug wire is removed and out of the way.
  4. Remove the six screws attaching the valve cover.
  5. Loosen the rocker jam nut; turn the pivot ball stud with a 13 mm Allen wrench while checking clearance with a feeler gauge to 0.002-0.004 in (0.05-0.1 mm).
  6. Hold the pivot ball stud in place and tighten the rocker arm jam nut to 174 in-lb (19.68 N-m); recheck clearance.
  7. Install new valve cover gasket, starting all six screws before tightening.
  8. Install the valve cover; tighten fasteners to 35-62 in/lb (4-7 Nm).
  9. Install the rubber plug into the fan screen.
  10. Install the spark plug and attach the spark plug wire.
  11. Install the back panel and enclosure top lid; tighten all fasteners securely.
  12. Place the generator in AUTO.
Check Valve Clearance adjustment

Tools: feeler gauge, socket wrench

  1. Cool engine before checking
  2. Turn generator OFF
  3. Remove enclosure lid fasteners, lid, and back panel
  4. Remove spark plug wire and spark plug
  5. Rotate flywheel nut clockwise to bring piston to TDC of compression stroke
  6. Check clearance between rocker arm and valve stem with feeler gauge
  7. If clearance is 0.002-0.004 in (0.05-0.1 mm), no adjustment needed
Battery Installation installation

⚠ Explosion hazard; connect positive cable first to avoid spark

⚠ Disconnect battery ground terminal before working on battery

  1. Verify generator is turned OFF
  2. Turn off utility power supply to transfer switch
  3. Remove 7.5A fuse from generator control panel
  4. Connect red battery cable (from starter contactor) to positive (+) post
  5. Connect black battery cable (from frame ground) to negative (–) post
  6. Install red battery post cover
  7. Install battery bracket and screw
  8. Install 7.5 Amp ATO fuse in control panel
  9. Assemble battery access panel with 2 hex head screws
  10. Assemble front door and top lid
Checking Gas Line Connections installation

Tools: Manometer

  1. Remove top lid and rear panel
  2. Check for leaks with non-corrosive gas leak detection fluid at all connection points
  3. Close gas supply valve
  4. Remove top gas pressure test port from regulator, install manometer
  5. Open gas supply valve and verify pressure is within specified values
  6. Close gas valve when completed
  7. Reinstall rear access panel and top lid
Electrical Checks installation

⚠ High voltage present at transfer switch and terminals

Tools: AC voltmeter, Frequency meter

  1. Verify generator OFF and main breaker OFF
  2. Turn OFF all breakers/loads powered by generator
  3. Turn on utility power to transfer switch
  4. Check utility voltage across N1-N2 (240VAC nominal) and N1/N2-neutral (120VAC nominal)
  5. Turn OFF utility power to transfer switch
  6. Push MANUAL button, engine should crank and start
  7. Let engine warm up 5 minutes, set main circuit breaker to ON
  8. Check output voltage across E1-E2 (236-240V at 62-63Hz) and E1/E2-neutral (118-120V)
  9. Set main breaker OFF, push generator OFF button
Fuel Conversion (NG to LP) installation

⚠ Connection of fuel source must be done by a qualified professional

Tools: 4mm and 6mm Allen wrenches, Needle nose pliers

  1. Remove four 6mm Allen fasteners and lift top lid
  2. Remove two 4mm Allen fasteners, lift and remove rear panel
  3. Squeeze hose clamp and slide from fuel inlet
  4. Remove hose from fuel inlet
  5. Remove NG fuel jet from fuel inlet
  6. Locate LP fuel jet (supplied, smaller ID than NG jet)
  7. Insert LP fuel jet into end of fuel inlet
  8. Reinstall hose on fuel inlet, secure with clamp
  9. Verify hose is not kinked
  10. Reinstall rear access panel and top lid
Generator Activation installation
  1. Obtain activation code via www.generac.com or 1-888-9ACTIVATE using unit serial number
  2. Hold OFF button for 3 seconds until all LEDs flash twice
  3. Enter 6-press activation code sequence using AUTO/OFF/SET EXERCISE buttons within 20 seconds
  4. If incorrect, AUTO/OFF/MANUAL buttons flash 3 times; retry
  5. If correct, all LEDs scroll bottom to top 5 times and OFF button lights
Battery Maintenance maintenance

⚠ Remove 7.5 Amp fuse before working on battery

⚠ Wear eye protection and rubber gloves

  1. Lift lid, remove front panel and battery access panel with generator shut down
  2. Inspect battery posts and cables for tightness and corrosion, tighten/clean as necessary
  3. Check battery fluid level of unsealed batteries, fill with distilled water only if necessary
Changing the Engine Air Cleaner maintenance
  1. Remove top lid with generator shut down
  2. Disengage wire clip and remove air cleaner access cover
  3. Remove old air filter and discard
  4. Clean air cleaner enclosure of dust/debris without letting debris fall into intake
  5. Install new air filter
  6. Install air cleaner cover and engage wire clip
  7. Install enclosure top lid, tighten fasteners securely
  8. Place generator in AUTO
Changing the Oil maintenance

⚠ Allow engine to cool before draining oil

Tools: hex head screwdriver

  1. Start engine via MANUAL button, run until warmed up, then press OFF
  2. Remove enclosure top lid and front panel
  3. Remove battery access panel (2 hex head screws)
  4. Disconnect battery and remove fuse
  5. Pull oil drain hose free of retaining clip
  6. Remove cap from hose, direct into container
  7. Unscrew drain hose cap, drain oil (remove dipstick to drain faster)
  8. Replace drain hose cap and secure with retaining clip
  9. Refill engine with recommended oil
  10. Connect battery, secure access panel, insert fuse, switch to MANUAL
  11. Start engine, run 1 minute, check for leaks
  12. Shutdown engine, check oil level, add as needed, do not overfill
  13. Insert dipstick/fill cap
  14. Press AUTO button
  15. Dispose of used oil and filter at proper collection center
Checking Engine Oil Level maintenance
  1. Turn OFF all associated loads via electrical panel main disconnect if running during outage
  2. Turn generator main circuit breaker to OFF
  3. Press control panel OFF button
  4. Remove 7.5 Amp fuse from control panel
  5. Remove enclosure top lid and front panel
  6. Remove dipstick/fill cap and wipe dry
  7. Insert dipstick without threading, remove again, verify level at H mark
  8. Add oil if necessary to FULL mark
  9. Turn main circuit breaker ON if running during outage
  10. Install 7.5 Amp fuse
  11. Press control panel AUTO button
  12. Turn ON needed loads

Extracted from the manufacturer documentation linked to this model. Values are copied as printed; confirm against your unit's manual and serial number.

Voltage reconnection

VoltagePhaseConnectionLeadsNotes
Transfer Control Signal WireWHITE #5Terminal E, wire 23
12 VDCTransfer Controls (+)RED #4Terminal D, wire 194
120VAC fused1T1 - Battery ChargerBLUE #3Terminal B; must be connected to keep battery charged
240 VAC sensing1N1 & N2 - Utility Dropout/Pickup SensingYELLOW #1 & #2Terminal A
DCDC (–) Common Ground WireBLACK #3Terminal C; required if paired with Generac Smart Power transfer switch

Extracted from the manufacturer documentation linked to this model. Values are copied as printed; confirm against your unit's manual and serial number.

Common questions

What is the oil capacity of the GA-420?

The GA-420 engine has an oil capacity of 1.1 liters.

What is the displacement of the GA-420?

The GA-420 has a displacement of 25.6 liters with 1 cylinders.

Which generators use the GA-420 engine?

The GA-420 powers 2 generator set(s), including Generac 7 kW PowerPact, Generac 7.5 kW PowerPact.

How often should you change the oil in the GA-420?

The GA-420 oil change interval is every 100 hours.

What is a common problem with the GA-420 engine?

A commonly reported issue on generators using the GA-420 is: Unit consumes large amounts of oil.. Cause: 1. Engine overfilled with oil. 2. Engine breather defective. 3. Improper type or viscosity of oil. 4. Damaged gasket, seal or hose.. Fix: 1. Adjust oil to proper level. 2. * 3. See Engine Oil Requirements. 4. Check for oil leaks..